$149,400 Added to Sierra Leone Power Outage Study, Bringing Contract to $1.65 Million
A $149,399.99 amendment funds 100 more sensors at five additional low-voltage sites in Sierra Leone and brings the outage study contract to $1.65 million.

SIERRA LEONE — Millennium Challenge Account–Sierra Leone added $149,399.99 to its power outage study, bringing the contract to $1,649,020.99. The change funds 100 additional sensors across five more low-voltage sites. It also expands the fieldwork and analysis behind the study.
“For nLine, installing the sensors is only part of the job. Field technicians and analysts have to connect each reading to a verified location before they can compare service across the seven sites.”
Professional Overseas Contractors editorial analysis
Millennium Challenge Account–Sierra Leone manages the local procurement under the energy compact funded by the U.S. Millennium Challenge Corporation. The local agency signed the amendment with nLine Inc. on November 9. The original contract, signed in March, was worth $1,499,621.
How the power outage study will expand
The five new sites will bring the number of fully instrumented low-voltage sites to seven. Alongside the sensor work, the contractor will map and verify field data and incorporate administrative records. A statistician or econometrician will join the team to analyze the expanded dataset.
The team will then revise the report that sets out how it measures outages. The amendment retains the original 36-month contract term. The procurement reference is SLCDU-24-4003.