U.S. Embassy Kabul Construction Bulge: From $625M to $773M, Est. Completion Date 2016


Professional Overseas Contractors
The Government Accountability Office (GAO) recently evaluated the construction of U.S. Embassy Kabul due to “broad congressional interest” in the oversight and accountability of U.S. funds used in Afghanistan. The GAO wanted to see what contracts State put in place to construct new U.S. embassy facilities in Kabul starting in 2009; the extent to which construction requirements, cost, or schedule have changed, and the reasons for the changes; and the extent to which the present expansion matches projected needs.

The GAO reports that contract costs for construction have increased by nearly 24 percent, from $625.4 million to $773.9 million as of May 2014. The original construction completion was to be the end of summer 2014; the contractual delivery date for all permanent facilities is now anticipated for July 2016.

With the withdrawal of U.S. troops in the horizon, SIGAR recently said that “constraint on oversight of US-funded Afghan reconstruction will only worsen as more US coalition bases close” and that the “ability to monitor, manage & oversee reconstruction programs in Afghanistan will only become more difficult.”

And yet, Embassy Kabul’s permanent facilities—both older and newly-constructed office and apartment buildings—will eventually contain 1,487 desks and 819 beds. The projected embassy staffing for 2015 is approximately 600 U.S. direct hires and 1,100 locally employed staff. Without the military support, State would once more end up with potentially contracting its own security and life-support contractors as it did in Iraq.